How to write a manufacturing RFQ that gets comparable quotes

Give every supplier the same scope, separate requirements from preferences, and ask for exceptions in writing. Use the example below to build your first RFQ.

By Abhi6 min read
In this article

The short answer

A manufacturing request for quotation should define what you need made, which revision controls, how many units you want, how the parts will be accepted, and when and where they must arrive. Ask suppliers to separate one-time charges from recurring part prices and identify anything they cannot meet.

An RFQ is most useful when it creates a common basis for comparison. Three totals are not comparable if one includes finishing, another excludes inspection, and a third assumes a different material. Use this guide to build the package before you contact US manufacturers.

Decide whether you need a quote or engineering help

If the design, material or acceptance criteria are still open, say so. Ask for a budget estimate or a paid engineering proposal rather than describing an unfinished concept as a released production order.

Our suggested first decision is simple: can a supplier manufacture and inspect the item without making an unresolved design choice for you? If not, list the open questions and name the person who will resolve them. You can still ask about feasibility, minimum quantities and a planning schedule. Keep that conversation separate from a firm quotation against released files. This helps you avoid treating an early estimate as a production commitment.

Practical takeaway: Put “budget estimate” or “production RFQ” in the subject line.

Create a controlled file package

Include the part number, drawing revision, CAD revision, units and the files that define the work. Fictiv’s quoting instructions recommend a PDF drawing for critical dimensions, threads, tolerances and finishing information.

Use one clearly named package rather than several conflicting email attachments. A suggested naming pattern is BRK-104_RevB.step and BRK-104_RevB.pdf. Add a short attachment register so the supplier can confirm what it received. State how conflicts between the model, drawing and RFQ should be raised, and require written resolution before manufacture. Do not assume an upload platform or shop uses your preferred order of precedence. Remove obsolete revisions from the active package.

Practical takeaway: Ask the supplier to repeat the quoted revision on its quotation.

Specify quantities without turning forecasts into orders

Separate the immediate order from possible future demand. Request distinct quantity breaks only where those quantities are realistic purchasing options.

For example, a hypothetical launch might need 25 evaluation units, followed by a possible 250-unit release after testing. Ask for both prices, but state that the larger quantity is a forecast and identify whether the supplier should assume one delivery or multiple releases. Also ask about minimum order value, setup charges and whether pricing depends on buying all the material at once. This makes the commercial assumptions visible before you compare the unit prices.

Practical takeaway: Give a first-order quantity, forecast quantity and proposed release pattern.

Define material, finish and acceptance

Specify the required material grade and condition, finish, critical features and the evidence you expect with delivery. Invite alternatives only if your engineering owner can evaluate them.

Keep requirements connected to function. If a surface must remain uncoated for electrical contact, identify it. If dimensions apply after finishing, say so. Describe whether you need a material certificate, a dimensional report, traceability or an approved sample before the remaining lot ships. Avoid adding a certification acronym simply because another buyer used it. Where certification is required, check the producing site and scope using our supplier certification guide.

Practical takeaway: Ask suppliers to price optional reports separately when they are genuinely optional.

Make the delivery requirement unambiguous

Distinguish a required arrival date from a preferred ship date. Give the destination and ask what event starts the quoted lead time.

A quote may measure lead time from order acceptance, payment, drawing approval or material receipt. Ask the supplier to name its starting condition and list the decisions it needs from you. For tooling or a new process, request milestones for design approval, first samples and production release. State whether partial shipments are useful. These questions are editorial purchasing recommendations; actual dates and terms need agreement with the supplier.

Practical takeaway: Request a schedule with dependencies, rather than accepting an unexplained number of weeks.

Use this sample RFQ message

The following is a hypothetical message to adapt after your files are ready. Its quantities and dates describe an example, not a recommended order size or supplier promise.

Subject: Production RFQ — BRK-104 Rev B — 25 and 250 units. Please quote the attached STEP model and PDF drawing, both Rev B, using the material, finish and inspection requirements on the drawing. Quote 25 units for evaluation and a separate 250-unit production option; the larger quantity is a forecast, not a commitment. State unit price, setup or tooling charges, inspection charges, packaging and freight assumptions. Confirm the quoted revision, material availability, producing location, lead-time start condition and earliest arrival at our delivery ZIP code. List exclusions, deviations, outsourced operations and quote validity. Please acknowledge the package and tell us when you can return the quotation. Direct technical questions to the named engineering contact.

Practical takeaway: Replace every placeholder and remove requirements that do not apply.

Compare scope before comparing totals

Use a comparison sheet with one supplier per row. Record revision, material, finish, quantity, one-time charges, inspection, delivery assumptions and exceptions.

A lower total may reflect an excluded operation rather than a more efficient shop. Send a clarification round to resolve differences and record the final answers alongside each quote. If one supplier proposes a design change, keep its alternative separate from the original scope until engineering approves it. For machining-specific questions, use the CNC quote checklist. Then shortlist suppliers by accepted scope and execution fit, not just the headline price.

Practical takeaway: Keep the agreed quotation and technical clarifications with the purchase order.

Frequently asked questions

Can I send an RFQ without a CAD model?

Yes, but explain what you have and what remains to be developed. Some suppliers can work from drawings, samples or sketches; others need a model. Ask which engineering work is included and who owns the resulting files.

How many suppliers should receive the RFQ?

Choose a manageable shortlist with evidence of process fit. Our editorial suggestion is to favor a few relevant shops you can follow up with over a broad, untargeted mailing. No fixed number guarantees a useful response.

Is an RFQ the same as a purchase order?

An RFQ asks for pricing and terms. It does not by itself communicate your final authorization to manufacture. Confirm the supplier’s ordering process and make sure the accepted scope is reflected in the purchase documents.

Sources

The pages this guide cites, in the order they appear.

  1. Fictiv’s quoting instructions · fictiv.com

Get 3 free quotes

Free, no account. One form, quotes from 3 matched US manufacturers. Bulk and wholesale orders welcome.