First article inspection explained: what to require and what to check
How to use first article inspection (FAI) when you qualify a new part or a new manufacturer. The AS9102 forms, full versus partial FAI, what to look for in the report, and where PPAP fits.
In this article
The short answer
First article inspection (FAI) is a documented check of a part from the first production run. It shows that the process the manufacturer will use for every later order made a part that meets every requirement on the drawing and purchase order. The IAQG's 9102 FAQ puts its value plainly: it validates that the production processes can make parts that meet the engineering and design requirements. The output is a First Article Inspection Report, or FAIR.
In aerospace and defense the report format comes from the 9102 standard, sold in the US by SAE as AS9102. The current revision is C. It uses three forms: one for the part, one for materials, special processes and functional tests, and one for the result of every design characteristic. You can ask for FAI outside aerospace too. The IAQG says the standard can be used in any sector that wants a standardized FAI process. Automotive buyers usually ask for PPAP instead.
This is general sourcing information. Your customer's flow-down requirements and your quality team decide what applies to your part.
Know what an FAI proves, and what it doesn't
An FAI shows that the planned process, material, tooling and inspection produced one part that met every requirement. That's all. The IAQG's Rev B to Rev C summary of changes added a line saying FAI is not a product acceptance document.
So an approved FAIR doesn't replace receiving inspection on later orders. It gives you a baseline: how the part was made and measured the first time it met the drawing. The FAQ also says the inspection has to be independent. The person who verifies a characteristic can't be the person who produced it, and the measuring equipment has to be different from the equipment that made it. Ask how a small manufacturer handles that when one machinist programs, runs and measures the job. One caution on sources: the FAQ was written for Rev B. The IAQG says its guidance has been folded into the Rev C standard and the FAI manual in its free Supply Chain Management Handbook (SCMH).
Practical takeaway: Keep lot acceptance requirements in every purchase order, even after the FAIR is approved.
Decide when to require it
Ask for FAI when a manufacturer makes a part for you for the first time, when a part moves to a new source, or when a bad first lot would hurt you badly. Federal buyers use similar logic. FAR 9.303 lists the cases where first article testing may be appropriate.
Under FAR 9.303, it may be appropriate when the contractor hasn't supplied the product before, or has but processes or specifications changed, production stopped for an extended period, or the product developed a problem in service. It also fits when the product is described by a performance specification, or when an approved first article has to serve as a manufacturing standard. FAR 9.304 says it's normally not needed for R&D, products normally sold in the commercial market, or parts covered by complete and detailed specifications, unless the requirements are novel or exacting. And FAR 9.302 asks contracting officers to weigh cost, delivery time, the risk of skipping it and cheaper ways to get the same confidence. That's a fair test for commercial buyers too. Just remember FAR first article testing is a government contract procedure, not an AS9102 report.
Practical takeaway: Put the FAI requirement in the RFQ so it's priced into the quote, not argued about after award.
Write it into the RFQ and purchase order
Say that FAI is required, which standard and revision the report follows, if you must approve the FAIR before parts ship, and if you want to witness the inspection. Then send the package to CNC machining companies or sheet metal fabrication companies that can quote to it.
For a real example of how a large buyer words this, read Lockheed Martin MFC's supplier FAI guidebook. It's a reference document, not a contract, and it covers only Lockheed Martin Missiles and Fire Control orders. When the PO note applies, an MFC supplier quality representative has to accept the FAI results before material ships, and suppliers must request a new or partial FAI at least 10 working days ahead so the buyer can attend. You don't need to copy those terms. But decide your own: who reviews the FAIR, how many days you need, and who carries the risk on parts made before approval. On government contracts, FAR 9.305 normally puts that risk on the contractor. Our manufacturing RFQ guide covers the rest of the package.
Practical takeaway: Ask each manufacturer if it has written AS9102 reports before, and ask to see a redacted one.
Check Form 1: part number accountability
Form 1 identifies the part being inspected, its drawing and revision, and any detail parts or sub-assemblies. Lockheed's guidebook describes it as the form that identifies the detail part, subassembly or assembly getting the FAI.
Start with the part number, the part revision and the drawing revision. The IAQG FAQ separates the two revisions: part revision is what's marked on the part, drawing revision is the revision of the drawing or digital model used. Field 9 ties the FAI part to the router or manufacturing plan that made it, and the FAQ accepts any reference that gives that traceability. Field 14 says whether it's a full or partial FAI. Rev C added a reason for a full FAI there, and a partial FAI points back to its baseline. Rev C also changed field 19. It used to be FAI complete or not complete. Now it asks whether the FAIR contains a documented nonconformance. For an assembly, check that every detail part and sub-assembly is listed.
Practical takeaway: If the drawing revision on Form 1 doesn't match your purchase order, send the report back before you read anything else.
Check Form 2: materials, special processes and tests
Form 2 lists the materials, special processes and functional tests the drawing calls for, who supplied each one, and the certificate or report number that backs it up. Lockheed's guidebook says it's used when any of those are defined as design characteristics.
For each line, look for the specification and its revision, the supplier's name and address, and the certificate or acceptance report number. The IAQG FAQ says the name and address are required even when a supplier code exists. If heat treat, plating, anodizing, welding or NDT went to an outside processor, that processor should be on this form. If your drawing or customer requires approved processors, field 9 (customer approval verification) is where the report shows it. And if you need Nadcap accreditation for a process, check it yourself in eAuditNet. Our certification verification guide shows how.
Practical takeaway: Match every material and finish note on the drawing to a line on Form 2.
Check Form 3 and the ballooned drawing
Form 3 lists every design characteristic with its requirement, the measured result and the tool used to measure it. Read it first. It's where most problems show up. A ballooned drawing numbers each characteristic so you can trace a result back to the drawing.
The IAQG FAQ says 9102 doesn't require a ballooned drawing. It does require every design characteristic to be accounted for, uniquely identified and traceable to its result. Lockheed strongly recommends ballooning anyway. Its list of common rejection causes includes dimensions or notes not accounted for, and writing “accept” or “OK” where a measurement was needed. If results come from a CMM, the FAQ says the attached report has to link to the characteristic numbers and show results you can compare to the requirement. For a positional tolerance you want the actual positional value, not raw coordinates. And check that each gauge listed can actually resolve the tolerance it measured.
Practical takeaway: Pick five balloons at random and trace each one from the drawing to Form 3 to the raw data.
Know when a partial FAI is enough
A partial FAI re-inspects only the characteristics a change could affect, and it references the baseline report. A full FAI repeats everything. Ask each manufacturer to show you its written rule for deciding between them.
Lockheed's guidebook lists the triggers for a partial FAI: a design change; a change in manufacturing source, process, inspection method, location, tooling or material; a change to NC programs or translation to another media; a natural or man-made event that may affect the process; and a corrective action needed to finish an earlier FAI. On a lapse in production, the IAQG FAQ says FAI is required for any characteristics the inactivity may have affected. Lockheed sets the allowed break in the purchase order. Rev C changed the test, too. Section 4.6 now requires a documented process to evaluate changes, and asks which characteristics are invalidated or not represented instead of the old fit, form or function wording. One rule hasn't changed. The original forms are never altered. A partial FAI uses Form 1 plus only the forms needed to record the change.
Practical takeaway: Require advance notice of any change in source, location, process or NC program, so you can decide if a partial FAI is needed.
Don't approve an FAI with an open nonconformance
If a characteristic fails, the report should say so. Rev C asks on Form 1 whether the FAIR contains a documented nonconformance. Under the Rev B FAQ, an FAI with a nonconforming design characteristic isn't complete until the fix is verified.
The FAQ lays out the steps. Record the nonconforming characteristic on Form 3 with the nonconformance report number. Fix the cause. Then run a partial FAI on the affected characteristics in the next production run. If that partial FAI doesn't clear every nonconformance, the FAI still isn't complete. The standard doesn't decide what happens to the bad parts. That's your call, under your purchase order and quality agreement. Once it's closed, file the accepted FAIR, the drawing revision and the corrective action together. The next order then starts from a known baseline.
Practical takeaway: Ask for the root cause and corrective action, not just a re-measured part.
Know how FAI differs from PPAP
PPAP is the automotive Production Part Approval Process, published by the Automotive Industry Action Group. AIAG describes PPAP as the industry standard for approving production parts so that engineering design record and specification requirements are met consistently.
The difference is in that word, consistently. An FAI documents that a first production part met every requirement. A PPAP asks the supplier to show it will keep meeting them, and it's a bigger package. Texas Instruments' PPAP page says TI follows the AIAG PPAP manual, 4th edition, that a TI package can run to as many as 18 elements depending on the level requested, and that AIAG defines five submission levels. Level 1 is the Part Submission Warrant (PSW) only. The customer picks the level. So ask automotive parts manufacturers for PPAP at the level your customer names, and ask aerospace suppliers for AS9102. Don't assume one package satisfies the other sector's customer.
Practical takeaway: Ask your own customer which approval it wants before you ask suppliers to quote.
Frequently asked questions
What is first article inspection?
- A documented inspection of a part from the first production run against every requirement on the drawing and purchase order. The report, called a FAIR, shows the production process can make a good part. Aerospace uses the 9102 standard (SAE AS9102).
What are the three AS9102 forms?
- Form 1 is part number accountability: the part, drawing, revisions and any sub-parts. Form 2 is product accountability for materials, special processes and functional tests. Form 3 is characteristic accountability: each design characteristic, its requirement, the result and the measuring tool.
Is a ballooned drawing required for AS9102?
- No. The IAQG's 9102 FAQ says the standard doesn't require one. It does require every characteristic to be uniquely identified and traceable to its result, and ballooning is the usual way to do that. Some customers, Lockheed Martin MFC for example, strongly recommend it.
When is a partial FAI required?
- When a change could affect some characteristics but not all. Lockheed Martin MFC's guidebook, for example, lists a design change, a new source, process, location, tooling, material or NC program, and a corrective action from an earlier FAI. A production break longer than the purchase order allows also triggers one there. Your purchase order and the manufacturer's FAI procedure set the exact rules.
Can a prototype be used for first article inspection?
- Not usually. The IAQG FAQ says development and prototype parts not meant for production use aren't part of the first production run. Lockheed's guidebook says FAI hardware should come from the first production run and shouldn't be a qualification unit.
Can a manufacturer use its own FAI forms?
- Yes, according to the IAQG FAQ, as long as the forms ask for all the required and conditionally required information and keep the same field numbers as the forms in the standard.
What is the difference between FAI and PPAP?
- FAI documents that a first production part met every requirement, and it's the aerospace norm under AS9102. PPAP is the automotive approval process from AIAG. It asks the supplier to show requirements will be met consistently, and its package can include many more documents, depending on the submission level the customer picks.
Sources
The pages this guide cites, in the order they appear.
- 9102 FAQ · iaqg.org
- IAQG says · iaqg.org
- Rev B to Rev C summary of changes · iaqg.org
- FAR 9.303 · acquisition.gov
- Lockheed Martin MFC's supplier FAI guidebook · f35.com
- AIAG describes PPAP · aiag.org
- Texas Instruments' PPAP page · ti.com